With the new Avicarvil slaughterhouse in Frâncești in operation, the old slaughterhouse on the same site lost its original purpose — but not its usefulness. PPAE converted it completely: the 1980s building now houses two new processing sections, Convenience and Semi-prepared food, extending the Carmistin group's value chain towards higher value-added products. PPAE acted as General Designer.
Challenges
Unlike the new slaughterhouse, built from scratch, the challenge here was intervening in an existing building — a slaughterhouse erected in the 1980s and extended many times over the decades. Each extension phase had left behind different structures, levels and routes, so the building concealed numerous constraints, many impossible to anticipate before opening up the walls: floor levels that do not match, heterogeneous structures, overlapping services. On top of this came the strict sanitary-veterinary requirements of a food-processing facility, which the new sections had to meet in full.
Solutions
PPAE re-partitioned and re-purposed the building to house the two sections — Convenience and Semi-prepared food — with the flows, zone separations and equipment required by food-safety regulations. Where the existing space was not enough, the intervention was completed with targeted extensions, and the façades were modified for the new function and image. The solutions were adapted step by step to the constraints discovered along the way, integrating the structures inherited from the different construction phases into a coherent functional whole.
Result
For Avicarvil and the Carmistin group, an old building turned into a new productive investment — two sections that extend the La Provincia brand's range towards convenience and semi-prepared products, making use of an existing structure instead of building from scratch. For PPAE, a natural continuation of the Frâncești slaughterhouse project and a demonstration of the ability to work not only on new buildings, but also on difficult interventions in existing ones, with all the surprises they hide.
Do you have an existing industrial building you want to convert to a new use? The PPAE team can support your project from concept to completion. Contact us
Holland Farming Agro - Hala depozitare produse pentru agricultura si sediu administrativ
Intermeat - Animal Waste Treatment Plant
Avicarvil - Poultry Processing Unit 13.500/hr
Avicarvil - Poultry Processing Unit Extension
Pajo Agriculture - Compound feed factory
Agronicolescu - Swine Farm Complex